TEEMA Industry Day 2026: modular AI data centres and the question of power
What Foxconn showed in Warsaw and why energy has become the main condition for new data centres

TEEMA Technology Park Industry Day took place in Warsaw on 17-18 November 2026, with Taiwanese technology companies presenting solutions for the AI era. Foxconn drew the most attention with a model of a data centre campus powered by the grid, solar and wind, battery energy storage (BESS) and fuel cells. Data centres are increasingly built from modules and can go up in months. A large grid connection takes far longer, so power is becoming the main condition for new projects, including in Poland.
- World, 2030
- 945 TWh
- data centre electricity use, more than double the 2024 level
- IEA, Energy and AI
- Modular build
- ≈6 months
- to deploy a modular data centre, against 2-3 years for a conventional one
- IEEE Spectrum
- PSE queue
- ≈14 GW
- of data centre connection capacity after the reform; before it, applications reached 150-200 GW
- ITwiz, PSE register, 30.09.2026
- Poland, mid-2030s
- ×10
- from 1.7-1.8 to 17-18 TWh a year of data centre consumption
- PSE, draft network development plan
The event
What is TEEMA Technology Park Industry Day?
It is a two-day event of the Taiwan Electrical and Electronic Manufacturers’ Association (TEEMA): an exhibition, a forum and B2B meetings. The 2026 theme was technology ecosystems for the AI era: data centres, smart manufacturing, e-mobility and smart cities.
According to TEEMA, about 50 Taiwanese companies from ICT, machine tools and electric vehicles came to Warsaw, and the organisers planned more than 100 one-to-one B2B meetings with Polish buyers and partners. The event was organised by TEEMA and the Bureau of Foreign Trade (BOFT) with the support of Taiwan’s Ministry of Economic Affairs (TEEMA via Cnyes).
TEEMA has been active since 1948 (TEEMA) and brings together more than 3,000 Taiwanese companies (PAIH). It is chaired by Young-Way Liu, chairman of Hon Hai Technology Group (UDN). In June 2026, at Taiwan Expo in Warsaw, the construction of a TEEMA technology park in Miękinia near Wrocław was confirmed (Polish Ministry of Development and Technology; XYZ.pl). According to Liu, TEEMA parks focus on three supply chains: AI data centres, smart cities and electric vehicles (UDN).
Hon Hai Technology Group (Foxconn) is one of the world’s leading electronics contract manufacturers and a major supplier of servers for training and running AI models (ITwiz).
Video
What did TEEMA Industry Day 2026 look like?
We filmed a short report from the first day: the opening, the main stage and the Foxconn stand with its data centre campus model. The video runs 76 seconds.
- TEEMA Industry Day, Hilton Warsaw
- Opening ceremony and agenda
- Main stage and the Foxconn stand
- One campus, four power sources
- the nech at the Foxconn stand
Foxconn stand
What did Foxconn show at TEEMA Industry Day 2026?
The centrepiece of the stand was a large model of an AI data centre campus where power was designed together with the server halls, not added at the end.
The model showed four power sources. First, a grid connection. Second, solar and wind plants. Third, battery energy storage (BESS), which stabilises supply and keeps the campus running through fluctuations in the grid and in renewable output. Fourth, fuel cells that generate electricity on site, with their heat returned to the campus systems. Hydrogen was also discussed at the stand as a possible fuel for this generation.
A fuel cell produces electricity in an electrochemical reaction, without burning the fuel. The by-product is heat that can be used on site. The fuel can be natural gas, biomethane or hydrogen.
According to the organisers, the TEEMA exhibits also included modular data centres, AI server racks and liquid cooling (TEEMA via Cnyes). Every such rack needs stable power around the clock, and this requirement kept turning conversations about AI into conversations about energy.
Foxconn model · one campus, four sources
Grid
Connection and capacity from the national power system.
Solar and wind
Own solar and wind plants or direct contracts with them.
BESS
Stable parameters and continuity of operation.
Fuel cells
On-site generation and heat recovery.
A new generation
Why are data centres becoming modular?
Because demand for AI computing is growing faster than conventional construction can keep up. A modular data centre is assembled from factory-built blocks, so it can go live in months and grow step by step.
A modular data centre consists of blocks for computing, power and cooling that are integrated and tested in the factory. On site they are only installed and connected. Capacity grows by adding blocks, and part of the equipment can be moved to another site if needed.
Vertiv estimates that prefabricated solutions can cut construction time by up to 50% compared with conventional builds, depending on project scope and conditions (Vertiv). Developers of modular AI data centres, including LG CNS, expect to deploy them in about six months, against roughly two to three years for a conventional data centre (IEEE Spectrum).
Modular against conventional
Servers can be in place within half a year. Whether the grid has capacity for them depends on a completely different timeline.
This is where modularity runs into energy. A module can be built and shipped, but a connection of tens or hundreds of megawatts needs a substation, a line and approvals from the grid operator. That is why the Foxconn stand presented power as part of the data centre itself.
Geography
Why are data centres spread across regions and continents?
Data centres are built close to users, to energy sources and within the jurisdictions where data has to be stored. There is a parallel with distributed generation in energy, although the logic differs.
The IEA names the United States, China and Europe as the largest regions for data centre electricity use, with South-East Asia growing fast around a hub in Singapore and southern Malaysia (IEA). The EU plans to at least triple data centre capacity within five to seven years and to create up to seven AI gigafactories. Where data centres are already concentrated, grids cannot keep up: in Ireland they use almost a quarter of the country’s electricity, and new connections in the Dublin area are effectively frozen (The Page, citing Fortune).
In distributed generation, electricity is produced at many points so that the grid is more resilient and closer to the consumer. Data centres distribute computing and data rather than megawatts, but the principle is similar: do not keep everything in one place. Our view: new sites in Central Europe, including Poland, are appearing not only because of demand but also because the old hubs are hitting grid limits.
Energy
How much energy do data centres need and where will it come from?
In the IEA Base Case, global data centre electricity use more than doubles to around 945 TWh in 2030. That is slightly more than Japan consumes today (IEA).
From 2024 to 2030, data centre consumption grows by around 15% a year, more than four times faster than consumption in all other sectors (IEA). The IEA expects half of the global increase to be met by renewables supported by storage and the grid (IEA); in Europe, nuclear and renewables should reach 85% of data centre supply by 2030 (heise, citing the IEA). In its World Energy Outlook 2026, presented in November, the IEA again warns about grid strain: data centre consumption could reach 1,000 TWh by 2030 (Euronews).
As a result, data centres increasingly build their own generation. Oracle, for example, made Bloom Energy fuel cells a central part of the energy plan for its Project Jupiter campus in New Mexico (Oracle / Bloom Energy). In a Bloom Energy survey, industry leaders expect about 30% of sites to use on-site power as a primary source alongside the grid by 2030 (Bloom Energy). These are a manufacturer’s figures, but other sources point the same way.
- The grid remains the backbone, but a large connection takes years.
- Solar and wind lower cost and the CO₂ footprint, but without storage they do not give a round-the-clock profile.
- BESS smooths the profile, holds the parameters and can partly replace diesel backup.
- Fuel cells and gas generation provide baseload on site and a faster start.
A modular data centre can be set up in a few months. A stable high-capacity connection usually takes years. That is why power is designed together with the data centre, from day one.
the nech · Insights
Polish market
Why has power become the bottleneck for data centres in Poland?
The market is still small, but grid connection applications exceeded the peak demand of the whole country several times over. The 2026 reform filtered out most of them.
Commercial data centres in Poland have about 200 MW of IT capacity; the largest European markets (Germany, the UK, Ireland, the Netherlands) are 6-9 times bigger. Before the reform, the queue of data centre connection applications reached 150-200 GW against national peak demand of about 30 GW (ITwiz).
Amendments to the Energy Law in force since 30 April 2026 introduced an application fee (PLN 1 per kW, up to PLN 100,000) and an advance of PLN 60 per kW (up to PLN 6 million), cut the validity of connection conditions from two years to one and require the investor to show a building permit within 24 months. According to the PSE register of 30 September 2026, about 14 GW of connection capacity remained in the queue, or about 11 GW of IT capacity (ITwiz). PSE estimates that there are a dozen or so real investors, not hundreds (Gramwzielone.pl).
Connection queue against real plans
After the reform the queue shrank by about 90%, yet even the remainder is almost three times the capacity PSE plans for 2040.
| Indicator | Value | Source |
|---|---|---|
| Data centre consumption in Poland today | 1.7-1.8 TWh | ITwiz, about 1% of national consumption |
| PSE forecast for the mid-2030s | 17-18 TWh | draft PSE network development plan 2027-2036 |
| Operational capacity, 2031 forecast | over 550 MW | PLDCA and PwC Polska |
| Data centre capacity in the PSE plan | ≈5 GW in 2040 | PSE for Gramwzielone.pl |
| Largest single project in the queue | 4 GW | Baltic Data Center Campus, Choczewo (ITwiz) |
| Data centre capacity in Europe | ≈13 GW at end-2026 | CBRE via Eurobuild CEE |
The campus in Choczewo on the Baltic coast is telling: 4 GW of connection conditions, next to offshore wind connection points and a planned nuclear power plant (ITwiz). Large data centres in Poland look not just for land but for places where capacity exists or will exist. CBRE names limited access to power as a barrier for the data centre market across Europe (Eurobuild CEE).
For energy companies
What does this mean for energy companies in the Polish market?
Data centres are becoming a new group of customers for the energy sector: high capacity, round-the-clock operation and almost zero tolerance for interruptions.
Hybrid power calls for several competences at once: connections and HV/MV substations, solar and wind generation, energy storage, gas generation and CHP, and increasingly fuel cells. We cover the Polish storage market in our overview of BESS in Poland 2026 and grids in our article on offshore wind, grids and energy storage.
For a foreign supplier or EPC contractor, such a project means talking at the same time to the data centre developer, the grid operator and a local general contractor. Power decisions are made early, while the developer is still choosing the site. Those who arrive later usually get only a request for a price against a finished specification.
Ukrainian companies have hands-on experience here: years of work with backup power, storage and on-site generation during outages. We look at how this works in our overview of the energy storage market in Ukraine. Our view: in Polish data centre projects the question “where will the power come from” will be asked earlier and earlier, and that is the stage to be in the conversation.
Questions and answers
Frequently asked questions about data centres and their power
When and where did TEEMA Industry Day Poland 2026 take place?
TEEMA Technology Park Industry Day | Poland 2026 took place on 17-18 November 2026 at Hilton Warsaw, ul. Grzybowska 63, Warsaw. It was organised by TEEMA and the Bureau of Foreign Trade (BOFT) with the support of Taiwan’s Ministry of Economic Affairs.
What did Foxconn show at TEEMA Industry Day 2026?
A model of an AI data centre campus with four power sources: a grid connection, solar and wind plants, battery energy storage (BESS) and fuel cells whose heat is recovered.
What is a modular data centre?
It is a data centre built from factory blocks for computing, power and cooling, which are assembled and tested in the factory and only installed on site. According to manufacturers, such a facility can go live in about six months against two to three years for a conventional build, and capacity grows by adding blocks.
How much electricity will data centres use by 2030?
In the IEA Base Case (Energy and AI report), global data centre consumption more than doubles to around 945 TWh in 2030. That is slightly more than Japan consumes today.
How much data centre capacity is expected in Poland?
Commercial data centres in Poland currently have about 200 MW of IT capacity and use 1.7-1.8 TWh a year, about 1% of national consumption. PSE expects 17-18 TWh a year by the mid-2030s and about 5 GW of data centre capacity in 2040.
Why do data centres build their own generation and storage?
Because a large grid connection takes months or years, while a data centre needs stable power around the clock. Own generation (solar, wind, gas, fuel cells) and BESS allow an earlier start and higher supply reliability. In a Bloom Energy survey, industry leaders expect about 30% of sites to use on-site power as a primary source alongside the grid by 2030.
Author
About the author

Dima V. Nechyporenko · founder of the nech
Dima V. Nechyporenko is the founder of the nech, a strategic business development company based in Warsaw that helps engineering firms, EPC contractors, equipment manufacturers and developers enter new markets in energy, infrastructure and industry. He has 19+ years of experience in strategy and business development in energy; he was Regional Director EU and a board member at VOLTAGE Group Polska (solar plants, BESS, HV/MV substations) and strategy director at RWDI (Canada).
Bibliography
Sources
- Cnyes / uAnalyze: TEEMA on Industry Day in Warsaw, 50 companies and 100+ B2B meetings, 13.11.2026.
- PAIH: TEEMA announces plans to establish a technology park in Poland.
- Polish Ministry of Development and Technology: Poland and Taiwan strengthen economic and technological cooperation, 23.06.2026.
- UDN: Young-Way Liu, chairman of TEEMA and Hon Hai, on TEEMA parks (AIDC, smart city, EV).
- XYZ.pl: Foxconn and TEEMA technology park in Miękinia.
- ITwiz: Foxconn enters Poland, semiconductor and AI hub in Miękinia.
- TEEMA: association presentation (founded 1948).
- IEA: Energy and AI, Executive summary.
- IEA: Energy and AI, Energy demand from AI.
- IEA: press release on the Energy and AI report.
- Euronews: data centre energy consumption could double by 2030, IEA (World Energy Outlook 2026), 19.11.2026.
- heise online: share of nuclear and renewables in European data centre supply, according to the IEA.
- IEEE Spectrum: modular data centres for AI (Duos, LG CNS).
- Vertiv: What is a modular data center.
- Oracle / Bloom Energy: Powering AI Data Centers, How Fuel Cells Work, 27.04.2026.
- Bloom Energy: Data Center Solutions (industry survey).
- ITwiz: data centres and power grids, the Polish market, 19.11.2026.
- ITwiz: how much energy Polish data centres will need, 10.02.2026.
- Gramwzielone.pl: a dozen or so real data centre investors in Poland, not hundreds, 24.08.2026.
- Bank.pl: PLDCA and PwC Polska report on the data centre sector, 21.10.2026.
- Eurobuild CEE: Europe increases data centre capacity by a fifth (CBRE), 02.10.2026.
- The Page: Serhii Tokarev (Roosh) to Fortune on data centre restrictions in Europe.
- the nech, YouTube: TEEMA Industry Day Poland 2026: AI Data Centres and Energy, 17.11.2026.
Note. This article is for general information only. It is based on organisers’ announcements, publications by institutions and media as of 20 November 2026 and our own observations at the event. The description of the model at the Foxconn stand reflects what we saw on site, not an official project specification. Company names and trademarks belong to their owners and are used for identification only. Photo and video: the nech. If you represent an organisation mentioned here and see an inaccuracy, please write to us via the contact page.