Energy · Polish market

Offshore wind, grids and energy storage in Poland: where the demand is for foreign suppliers in 2026

Poland is building three things at once: offshore wind farms, power grids and energy storage. In 2026 the first offshore wind farm, Baltic Power, delivered power to the grid, PSE plans more than PLN 64 billion of grid investment to 2034, and about 5.1 GW of storage has already been contracted in the capacity market. Demand for equipment, substations, cables and EPC services is booked for years ahead, but the winners will be the companies that find local partners early and get through grid connection.

By the nechPublished Reading time 7 min

First offshore wind farm
1.1 GW, 76 turbinesBaltic Power, Northland Power
Offshore auction, Dec 2025
3.4 GWWindEurope
PSE investment to 2034
over PLN 64 bnPSE grid development plan
Storage in the capacity market
≈ 5.1 GWModo Energy, auctions 2022-2025

Offshore

What is happening with offshore wind in Poland right now?

Polish offshore wind has moved from plans to operation. In July 2026 the Baltic Power wind farm (ORLEN 51%, Northland Power 49%) delivered first power to the grid (ORLEN). It is 1.1 GW with 76 Vestas 15 MW turbines. In October 2026 all 76 turbines were installed, more than a third are already generating, and commercial operation is expected in 2026 (Northland Power).

The next wave is already contracted. In its first auction in December 2025 Poland awarded 3.4 GW to three Baltic projects: Baltic East (ORLEN), Baltica 9 (PGE) and Bałtyk I (Polenergia and Equinor), under 25-year contracts for difference (CfD). First power from them is planned for December 2032 (Notes from Poland), with further auctions set for 2027, 2029 and 2031 (WindEurope).

The long-term target, set in law, is 18 GW of offshore wind by 2040 (Recharge). For a supplier this is not one project but an order pipeline running 15 years ahead.

Supply chain

Where in the Polish supply chain is there room for foreign companies?

Poland is deliberately building its own industrial base for wind, but it cannot cover everything on its own. That creates demand for foreign manufacturers and partners.

Vestas already assembles offshore turbine nacelles in Szczecin: the first Polish-built nacelles were installed at Baltic Power in November 2025 (offshoreWIND.biz). At the same time, Vestas put its second Szczecin factory, for blades, on hold in October 2025 because European demand was lower than expected (offshoreWIND.biz). WindEurope estimates that Polish companies can supply more than 40% of the supply chain for new projects (WindEurope); imports and joint ventures will cover the rest.

At the Polish-German Economic Forum, participants in the energy round table pointed out that the Polish and German supply chains complement each other: some components are made in Poland, others in nearby factories in Germany and Denmark. At the same time every market in the region is building at once, so key components and skilled people are in short supply.

  1. Components

    Foundations, cables, substation equipment and specialist equipment that the local market lacks.

  2. Service and installation

    Operation and maintenance of the farms coming online from 2026, and installation work onshore and in ports.

  3. Joint ventures

    Localising part of production with a Polish partner to meet local content expectations.

Grids

Why have grids and connections become the main bottleneck?

Generation is growing faster than the grid can absorb it. The PSE transmission grid development plan for 2025-2034, agreed with the President of URE in December 2024, provides for more than PLN 64 billion of investment, 4,700 km of new 400 kV lines, 28 new substations and the upgrade of 110 existing ones, plus the evacuation of about 18 GW from offshore wind farms (PSE).

The cross-border side is growing too: PSE and the German operator 50Hertz have agreed to cooperate on a third interconnector between the two countries’ grids (PSE).

The other side is the connection queue. According to Modo Energy the total queue exceeds 240 GW, and real available capacity at 110 kV substations at the start of 2026 was zero (Modo Energy). For a foreign company this means checking connection conditions before promising a client any timeline.

Poland is building its energy system for decades ahead: offshore wind, grids and storage already have contracted money behind them. Companies that come now will build the market alongside it.

the nech · Insights

Storage

Who buys energy storage in Poland, and why?

Storage has become the most dynamic segment. Four capacity market auctions in 2022-2025 contracted about 5.1 GW of storage capacity for delivery in 2027-2030, which corresponds to at least 11 GW of physical batteries (Modo Energy).

The main buyers are developers holding capacity market contracts, generators that need flexibility, and industrial consumers. The NFOŚiGW fund has also supported 172 projects with PLN 4.15 billion, to be commissioned by 2028 (Modo Energy).

The more wind and solar on the system, the more batteries, thermal storage and fast data work matter. Price volatility then becomes a source of revenue rather than a cost. This is where demand for equipment, integrators and EPC contractors is highest.

Takeaways

What does this mean for a company entering Poland now?

The market does not need convincing that Poland’s energy transition will happen. It is already happening, and the money behind it is contracted. The question is who becomes a supplier in time.

  1. Start with the buyer, not the product

    Define exactly who buys: a developer, an EPC contractor, a grid operator or an industrial consumer. Channel and price depend on it.

  2. Check connection and regulation

    For storage and generation, connection conditions and URE requirements set timelines more than anything else.

  3. Find a local partner

    Local content expectations in offshore wind make a partnership with a Polish company a competitive advantage.

  4. Build relationships before the RFP

    Supplier decisions often take shape before the formal request for proposals. Those who arrive at the last minute compete on price alone.

We explain how to build that commercial presence in our article on hiring a head of sales in Poland, and we summarised the energy discussions in our report from the Polish-German Economic Forum 2026.

FAQ

Frequently asked questions.

How much offshore wind is Poland planning?

The first farm, the 1.1 GW Baltic Power, delivered power to the grid in July 2026. Another 3.4 GW was awarded in the December 2025 auction, and the law sets a target of 18 GW of offshore wind by 2040.

How much is PSE investing in the grid?

Under the agreed grid development plan for 2025-2034, PSE plans more than PLN 64 billion, 4,700 km of new 400 kV lines and 28 new substations.

How much energy storage has been contracted in Poland?

Four capacity market auctions in 2022-2025 contracted about 5.1 GW of storage capacity for delivery in 2027-2030.

What slows projects down most?

Grid connection: the queue exceeds 240 GW, and there was practically no free capacity at 110 kV substations at the start of 2026. Skilled people and key components are also scarce.

What does the nech do?

the nech (thenech.com) is a Warsaw-based outsourced commercial team for foreign energy companies entering Poland.

Disclaimer. This article reflects our view of the Polish market as of October 2026 and relies on the public sources listed above. It is general information, not investment, legal or technical advice.